Welcome to Hunterdon County, NJ

The Web     Hunterdon
CLOSURES AND PROJECTS
DEPARTMENT OF PUBLIC WORKS
ROAD AND BRIDGE CLOSURES AND PROJECTS BY MUNICIPALITY
SPECIAL PROJECTS AND PUBLIC HEARINGS
STATE PROJECTS
OTHER PROJECTS
COUNTY ENGINEER'S STATUS REPORTS OF CURRENT PROJECTS

 

 

ROAD & BRIDGE PROJECTS
ROAD & BRIDGE CLOSURE NOTICES

DEPARTMENT OF PUBLIC WORKS
Division of Roads, Bridges and Engineering

Route 12 County Complex, Building #1
PO Box 2900
Flemington, NJ 08822-2900
908-788-1227 | engineering@co.hunterdon.nj.us

Facebook Twitter

Hunterdon County Department of Public Works

KEY: NEW UPDATED ACTIVE COMPLETED

CLINTON TOWNSHIP

ACTIVE PROJECT

COUNTY BRIDGE C-65

 

C-65, County Route 639, Clinton Township:

  • Repairs being done to a masonry stone arch on County Route 639 in Clinton Township near the River Road intersection.
  • Bridge will not be closed during construction, minor delays should be expected

SOUTH BRANCH PUMPING STATION DREDGING PROJECT

DATED:
02/26/2020

SOUTH BRANCH PUMPING STATION DREDGING PROJECT: www.njwsa.org/sbps-dredging.html

FEBRUARY 26, 2020:

The Authority has authorized its contractor, Mount Construction, to begin work on a project that has been in the planning phase for some time: dredging of the intake pond and channel at the South Branch Pumping Station on River Road. Clinton Township residents along the truck route (which follows River Road to Lilac Road to Allerton Road to Route 31) will be mailed informational postcards on Tuesday, February 18. We have also created a new page on our website dedicated to the project, which is http://www.njwsa.org/sbps-dredging.html. The website has additional details that the postcard does not due to size limitations on the postcard.

Mount Construction has been advised to contact Township officials to confirm working hours and weight restrictions along the trucking route. They expect to begin work onsite in early March.

New Jersey Water Supply Authority
1851 State Route 31
P.O. Box 5196
Clinton, NJ 08809
908-638-6121
www.njwsa.org

ROUND VALLEY RESERVOIR PROJECT

LAST UPDATE:

ROAD CLOSURE 11/11/2019

ROUND VALLEY RESERVOIR PROJECT - www.roundvalleyproject.com

OCTOBER 30, 2019 UPDATE: Route 629 Road will be closed beginning on or about November 11, 2019 through the end of December 2019. A Detour will be posted.

SEPTEMBER 16, 2019:

Road closures Planned for County Route 629

Abutment Grouting and Road Closure Notification
Grouting of the abutments at the South Dam has been ongoing for the past few months. Work will shift to the North Dam this fall. In connection with work at the North Dam, the segment of County Route 629 that parallels the Reservoir between Old Mountain Road and the Boat Launching area is scheduled to be closed from sometime in October to mid to late December, 2019. Access to the Boat Launching area will remain open. Detour signage will be placed at both ends of the road closure. Any changes to these dates will be announced here.

Reservoir Drawdown Has Begun
In anticipation of the next phase of the Round Valley Project, the rehabilitation of its three earthen dams, the Authority has begun drawing down the Reservoir water level. The dam rehabilitation phase is the largest and final phase of work and site preparation is anticipated to begin in the late winter/early spring of 2020. The target maximum water elevation level for construction is 360’ and as of September 16, 2019, the level is 369.9 (full pool is 385’). The Authority plans to lower the pool at a rate of approximately 1 – 1.75 feet of elevation per week until the target level of 360’ is met. The pool will remain at or below this lowered level for the duration of the project, which is currently scheduled to be completed in late 2021. If drought occurs during construction and additional releases are necessary for water supply, the pool would naturally be reduced further. Additional details about this phase of the Round Valley Project, including water levels and a second closure of County Route 629 will be announced here as they are established.

 

{BACK}

 

 

 

 

 

 

GOVERNMENT

Board of Chosen Freeholders
County Clerk
County Prosecutor
County Sheriff
County Surrogate
Departments and Services
Hunterdon's Municipalities
State/Federal Elected Officials

PROGRAMS AND SERVICES

County Library  |  Economic Development  |  Emergency Notifications  |  Deer  Recovery Program  |  Farmland
Preservation
  |  Local Services Locator  | Municipal Tax Maps  |  Pothole Reporting  |  Road and Bridge Projects
Senior Services  |  Shared Services  |  Social Services  |  Transportation (the LINK)  |  Veterans Recognition Program

CONNECT WITH US
Facebook  Facebook
Twitter  Twitter
CONTACT

   
COUNTY OF HUNTERDON               (908) 788-1102
   71 Main Street, PO Box 2900          freeholders@co.hunterdon.nj.us
   Flemington, New Jersey 08822
  DISCLAIMER ACCESSIBILITY WWW.CO.HUNTERDON.NJ.US